Bid Pro Offshore

Pipeline Pig Launcher Install

DraftLump SumLLOG
Scope of Work$118,500.00
DescriptionLine Total
Launcher Fabrication & Prep$47,500.00
Offshore Installation$48,200.00
Tie-In & Pressure Testing$22,800.00
Scope Subtotal$118,500.00
+ Overhead (13%)$15,405.00
+ Profit (16%)$21,424.80
+ Contingency (10%)$15,532.98
Gross Margin30.6%
Notes

Preliminary scope only. Waiting on P&IDs from client engineering.

Grand Total$170,862.78
DraftSep 25, 2026
Update Status
Client
LLOG
Created
Aug 20, 2026
Due Date
Sep 25, 2026
Bid ID
bid-006
Bid Pro: Offshore Services v1.0LK Resource Connections, LLC