Bid Pro Offshore

Scaffold Erection — MC 252

LostT&MFieldwood
Labor$36,300.00
DescriptionTotal
Scaffold Foreman$9,900.00
Scaffold Builder$13,200.00
Scaffold Builder$13,200.00
Equipment$5,700.00
DescriptionTotal
Scaffold Material Set$5,700.00
Materials$1,200.00
DescriptionTotal
Consumables & Safety Supplies$1,200.00
Mobilization$3,800.00
Subtotal$47,000.00
Contingency (8%)$3,760.00
Notes

Lost on price. Competitor came in 12% lower.

Grand Total$50,760.00
LostAug 15, 2026
Update Status
Client
Fieldwood
Created
Jul 28, 2026
Due Date
Aug 15, 2026
Bid ID
bid-005