Labor$36,300.00
| Description | Total |
|---|---|
| Scaffold Foreman | $9,900.00 |
| Scaffold Builder | $13,200.00 |
| Scaffold Builder | $13,200.00 |
Equipment$5,700.00
| Description | Total |
|---|---|
| Scaffold Material Set | $5,700.00 |
Materials$1,200.00
| Description | Total |
|---|---|
| Consumables & Safety Supplies | $1,200.00 |
Mobilization$3,800.00
Subtotal$47,000.00
Contingency (8%)$3,760.00
Notes
Lost on price. Competitor came in 12% lower.
Grand Total$50,760.00
LostAug 15, 2026
Update Status
Client
Fieldwood
Created
Jul 28, 2026
Due Date
Aug 15, 2026
Bid ID
bid-005